MeerSOLAR FlowchartΒΆ
The pipeline follows several steps. By default, all steps are executed. If the user desires, they can selectively disable any step. However, the pipeline will only function correctly if its internal logic is maintained.
For example, if the user disables splitting the target scans and no target directory exists beforehand, imaging will not be performed. However, if self-calibration is disabled, the pipeline will skip that step and proceed with applying basic calibrations and generating final images.
Recommendation
It is recommended to go through the flowchart of the pipeline and understand it before modifying the pipeline keys.
Click here to see the MeerSOLAR pipeline flowchart
graph TD
Start([Start])
Decision1{HPC?}
Process1[Fluxcal with<br>noise-diode]
Process2[Target splitting<br>in parallel]
Decision2{Do basic<br>calibration?}
Process3[Make multi-ms using<br>calibrator scans]
Process4[Perform flagging<br>on calibrators]
Process4a[Simulate<br>calibrator<br>visibilities]
Process5[Perform basic<br>calibration]
Decision2a{Calibration<br>table<br>present?}
Decision3{Do<br>self<br>calibration?}
Process6[Apply basic<br>calibrations]
Decision1a{HPC?}
Process7[Target splitting<br>in parallel]
Process8[Perform<br>self-calibration]
Process9([Stop with<br>basic calibrated<br>visibilities])
Decision4{Self<br>calibration<br>successful?}
Process10[Apply<br>self-calibration]
Process11([Stop with<br>basic calibrated<br>visibilities])
Process12[Split raw<br>data of<br>target scans<br>for imaging]
Process13[Apply<br>basic calibrations]
Process14[Apply<br>self calibrations]
Process15[Perform imaging]
Process16([Finished with<br>final imaging<br>products])
Stop([Pipeline end])
Start --> Decision1
Decision1 -->|Y/N| Process1
Process1 --> Decision2
Decision1 -->|Y| Process2
Decision2 -->|Y| Process3
Process3 --> Process4 --> Process4a --> Process5
Process5 --> Decision2a
Decision2 -->|N| Decision2a
Decision2a -->|Y| Process6
Decision2a -->|N| Stop
Process6 --> Decision3
Decision3 -->|Y| Decision1a
Decision1a -->|Y| Process8
Decision1a -->|N| Process7 --> Process8
Process8 --> Decision4
Decision3 -->|N| Process9
Decision4 -->|Y| Process10 --> Process12 --> Process13 --> Process14 --> Process15 --> Process16
Decision4 -->|N| Process11